Activities June

7th of June, 2010 | Noord-Holland | press release

 

Tunnel
In the dry dock in Barendrecht, the construction of the tunnel elements is under progress. The construction of element 1 (of 4) is nearly completed. The construction of the ramps of the tunnel in Amsterdam is going well. The focus is now on reinforcement of the structural floors and the concrete can be poured. The construction of the separation wall between the existing tunnel and the newly constructed tunnel is progressing steadily. The wall is carefully lowered from a pontoon on the water and pushed into the deep channel bottom.

A10 West
Sand is consolidating on both sides of the A10 West. Around it, roads have been and will be diverted. Exit S101 from Westhavenweg and Kabelweg have been diverted. The new bridge over the Koelwatertunnel is in the completion phase and the foundation of the expansion of the viaduct is ready. The focus of the work will shift to the other crossings.

Coenplein/A8
The groundwork for the – to date unused - viaduct is in full swing. Also around this viaduct, the preparatory work for diversion of the roads has begun. The extended Stellingweg has been asphalted and diverted in the weekend of 5 June 2010.


<< Go back